When using Uniconta project, it is necessary to ensure the setup of the account assignment.
Account assignment for invoicing + timesheet
Overall, there are two types of invoicing: on account invoicing and regular project invoicing (Invoice proposal).
The idea in Uniconta is that a regular invoice proposal ends a period or a project.
On account invoices are invoices that provide capital, but no revenue in profit and loss in the general ledger module, as on account revenue is most often posted to a balance sheet account. This idea can be deviated from depending on whether work in progress with integration to ledger is used or not, so different scenarios must be considered.
In Uniconta, a project is complete when everything is invoiced and sales value = 0
Example 1 – On account + regular invoice without work in progress
Example of account assignment in connection with posting an on account invoice and a subsequent “final invoice”, where the on account invoice is offset. This is in a setup where work in progress posting is not set up.
| Project | Finance | |||||||
| On account invoice | ||||||||
| Text | Amount | VAT | Account | Account type | VAT | Debit | Credit | |
| On account | -10.000 | 2.500 | AC invoiced | Balance sheet (most often) | 10.000 | |||
| Customer summary account | Customer | 12,500 | ||||||
| VAT | vat payable | U25 | 2,500 | |||||
| Invoice proposal with offsetting of the on account amount | ||||||||
| Text | Amount | VAT | Account | Account type | VAT | Debit | Credit | |
| Revenue | -25.000 | -6.250 | Revenue | Profit and loss | U25 | 25.000 | ||
| On account | 10.000 | 2.500 | AC invoiced | Balance sheet (most often) | 10.000 | |||
| Total | -15.000 | 3.750 | Customer summary account | Customer | 18.750 | |||
| VAT | vat payable | U25 | 3,750 | |||||
Example 2 – Timesheet + on account + regular invoice with work in progress
Example of account assignment in connection with posting hours on the project, an on account invoice and a subsequent “final invoice”, where the on account invoice is offset and the hours are marked as invoiced. This is in a setup where work in progress posting is set up.
Note! The posting in finance should be posted to different accounts depending on whether you have chosen to post work in progress by cost or sales value. This example is based on sales value
| Project | To | Finance | ||||||
| Timesheet | ||||||||
| Text | Amount | VAT | Account | Account type | VAT | Debit | Credit | |
| 25 hours at DKK 1,000 | 25.000 | In progress | Balance sheet | 25.000 | ||||
| Expected revenue hours (sales value) | Profit and loss | 25.000 | ||||||
| On account invoice | ||||||||
| Text | Amount | VAT | Account | Account type | VAT | Debit | Credit | |
| On account | -10.000 | 2.500 | In progress | Balance sheet | 10.000 | |||
| Customer summary account | Customer | 12,500 | ||||||
| VAT | vat payable | U25 | 2,500 | |||||
| Invoice proposal | ||||||||
| Text | Amount | VAT | Account | Account type | VAT | Debit | Credit | |
| Revenue | -24.000 | -6.000 | Revenue | Profit and loss | U25 | 24.000 | ||
| On account | +10.000 | 2.500 | AC invoiced | Balance sheet (most often) | 10.000 | |||
| Total invoicing | -14.000 | -3.500 | Customer summary account | Profit and loss | 17.500 | |||
| Adjustment (the difference between the hours’ sales prices and what is invoiced) | -1.000 | VAT | Balance sheet | U25 | 3.500 | |||
| Work in progress | Balance sheet | 25,000 | ||||||
| Expected revenue hours (sales value) | Profit and loss | 25,000 | ||||||
| Over-/under-coverage + project adjustments | Profit and loss | 1,000 | 1,000 |
Setup of hour posting
The accounts that hours are posted to are set up on the project groups in the fields Labour (Offset account) and Labour (Post WIP).
The first of these accounts is used for the balance sheet account that will be debited and the other for the profit and loss account that will be credited.
Setup of on account posting
The accounts that on account revenue is posted to are set up, for example, on the item group used for the on account item number you have created for the purpose.
If it is not set up or an on account item number is not used, the revenue will be posted to the revenue accounts defined on the customer group. It is also from the customer group that the customer summary account is retrieved.
Setup of invoice proposal posting
The accounts that revenue is posted to are set up, for example, on the item group(s) linked to the item numbers used on the invoice lines.
If it is not set up or item numbers are not used on the invoice lines, the revenue will be posted to the revenue accounts defined on the customer group. It is also from the customer group that the customer summary account is retrieved.
If it is selected on the project group that work in progress should be posted, then the hours that are invoiced (i.e., the hours included in the invoice’s transaction origin) will be posted to the accounts defined on the project groups in the fields Labour (Offset account) and Labour (Post WIP). The first of these accounts is used for the balance sheet account that will be credited and the other for the profit and loss account that will be debited.
Note! If the fields Reverse WIP and Reverse WIP (Offset account) are filled in, then posting is made to these accounts instead.
If more or less is invoiced than the sales value of the records included in the transaction origin, an adjustment record is automatically posted on the project. This record is only posted in finance if you post work in progress by sales value.
The adjustment is posted to the accounts defined on the project groups in the fields Invoice adjustment (Offset account) and Invoice adjustment.
The first of the two accounts is debited and the other is credited if it is an under-coverage.